Power generation drops by 964MW on gas shortage
Power plant
The nation’s power generation capacity
has dropped from 4,285 megawatts recorded on September 16 to 3,321
megawatts on December 1 due to dearth of gas.
The figure was obtained from the website of Nigerian Electricity System Operator on Thursday.
The Transmission Company of Nigeria puts
the total output of all the generation companies at 3,321.50 megawatts,
which had been transferred to the 11 distribution companies across the
country.
An official of TCN, who preferred
anonymity, said that electricity generation had been dwindling due to
challenges of accessing gas by generation companies.
The official said that the country’s
power generation dropped from over 4,000 megawatts recorded in September
and October to 3,321.50 megawatts current recording as Dec. 1.
Similarly, a top management official of
Egbin Power Station, who also pleaded anonymity, said that the power
plant was generating over 1,000 megawatts.
He said the plant, which is located in
Lagos, now generates and distributes between 250 megawatts and 300
megawatts due to shortage of gas.
The official said that Egbin, with an
installed capacity of 1,320 megawatts, has the capacity to wheel over
1,000 megawatts daily.
He said that the plant is now limited to less than 300 megawatts due to shortage of gas.
Meanwhile, the General Manager,
Communications of the Eko Electricity Distribution Company Plc, Mr.
Godwin Idemudia, attributed recent frequent outages within the company’s
network to the drop in energy allocation to it.
Idemudia said that the company was receiving less than 300 megawatts instead of 1,300 megawatts needed to service its consumers.
He said that the company had reached
agreement with independent power companies to argument the little energy
being received from the national grid to meet energy demands of its
customers.
The Eko DISCO secured additional 160 megawatts of electricity to augment its allocation from the national grid.
He said, “We have entered into bilateral
agreements with Egbin Power Plc and Paras Energy & Natural
Resources Development Limited for 100 megawatts and 60 megawatts
respectively.
“But the generation companies are constrained by gas challenges.
“We are also working on embedded power programme aimed at producing 480 megawatts for distribution to our customers.”
Some residents of Ikosi, Arepo and
Obanikoro in Lagos within Ikeja Electric Distribution Company’s
operations had staged series of protests over power outages in their
areas.
The protesters, who came in their
hundreds, chanted songs to drive home their grievances and prevented
officials of the company and other consumers from entering the premises.
They carried placards with inscriptions
such as “All we are saying, give us supply’’ and “what is our offence
that Ikeja Electric refuses to give us electricity?’’
(NAN)